How to plan a home renovation: order of work, quotes and a realistic timeline

Last updated:

Renovations go wrong in the gaps: the tiler arrives before the plumber has finished, the kitchen units are delivered to a room with no floor. A clear sequence, a decision list and a time buffer prevent most of it.

Add the first quote deadlineOpen the moving checklist templateOpens in your browser — no install or sign-up needed.

Define scope and a ceiling before you call anyone

List what you want done, split into must-have, nice-to-have and later. Decide a total budget and hold back 10 to 15 percent for surprises, which are common in older homes where walls and pipes hide problems. Quotes are much easier to compare when each builder prices the same written scope.

The usual order of work

A common sequence for a full room refresh
StageTypical workWhy this order
1Demolition, structural changesDirty and noisy, so first
2Plumbing and electrics (first fix)Hidden inside walls and floors
3Plastering, then drying timeNeeds to dry before paint
4Flooring and fitted unitsBefore skirting and final decoration
5Painting, second fix, cleaningLast, to avoid damage

Keep a decision list with deadlines

Tiles, taps, worktops and light fittings often have lead times of several weeks. For each choice, note the date by which it must be ordered so the work is not waiting on you. Put those dates in your list as hard deadlines, with delivery dates and a note of where the receipt is.

Photograph walls before they are closed up so you know where pipes and cables run. It will save you when you hang a shelf later.

Managing trades and neighbours

Setting it up in Pladay

  1. Create a list for the project with each stage as a parent task and the details underneath.
  2. Add due dates for quotes, orders and deliveries, and count down with the D-day calculator.
  3. Track costs next to the plan using the approach in budget and to-do.
  4. Add a weekly check-in task with the contractor: “Site visit every thursday 5pm”.

Templates for this

FAQ

How much buffer should I add to the schedule?

Many people add 20 to 30 percent extra time on top of the contractor's estimate, because delays in deliveries and drying are common.

Do I need a permit?

It depends on the work and where you live. Check with your local authority before structural changes, windows or anything that affects a shared building.

Can Pladay store quotes and photos?

Pladay is for tasks, dates and notes. Keep files such as quotes and photos in your usual storage and link to them in the task notes.

Add the first quote deadline

Try it now, no sign-up needed

Pladay is a free to-do and day planner that works offline and keeps your data on your device first. Add tasks in plain language, repeat them, and plan a realistic day.

Start free — no sign-upDownload the appPladay